13.5 Calculate ES, LS, EF, LF and slack time for activities in Exercise 13.1
(see attached file for data)
13.1 Given the diagram shown in figure ex 13.1, with activities A through G and duration times
(see attached file for data)
a.
Activities Duration Time ES LS EF LF Slack Time Predecessor EF= ES+duration ES = EF of the predecessor activity LF = LS of the succeeding activity LS = LF – duration Slack time = ES-LS Slack time = …
This solution involves calculating for ES, LS, EF, LF, and slack time. Diagrams are also given.